Birdon awarded contract for Garden Island Redevelopment Project

Birdon awarded contract for Garden Island Redevelopment Project

NSW-based company Birdon has announced it has won the contract to undertake dredging works at Garden Island.

NSW-based company Birdon has announced it has won the contract to undertake dredging works at Garden Island.

Based in Port Macquarie, Birdon confirmed its split hopper barge “PELICAN” and backhoe dredge “BHD SYDNEY” have now arrived at Garden Island, and are ready to commence dredging works.

The company said it is "proud to be part of improving Australia’s Defence Force capabilities" in a release, and said that the dredging works will increase the depth of the berth pocket for naval vessels at Garden Island as part of an upgraded wharf infrastructure project.

==============
==============

It will include the supply, maintenance and operation of all equipment for the removal and disposal of a significant volume of dredged material from Sydney Harbour, using equipment tailored for operation in the local conditions, Birdon confirmed.

The work represents element three of stage two of the Garden Island Redevelopment Project, with Lendlease winning the $286 million contract to the second stage.

The elements of the project are as follows:

  • Project Element 1: Demolition of wharf structures;
  • Project Element 2: Construction of wharf structures;
  • Project Element 3: Seabed dredging;
  • Project Element 4: Wharf furniture;
  • Project Element 5: Portal crane; and
  • Project Element 6: Shore engineering services.

Stage two is estimated to be completed in "late 2023".

A summary of the original project timeline, as provided by Defence, is below:

 

Activity Anticipated commencement date Anticipated completion date
Phase 1
Set-up of site Mid Aug 2018 End Sep 2018
Demolition of the existing wharf Early Oct 2018 Mid Apr 2019
Construction of the new wharf Mid Jan 2019 Early Dec 2019
Dredging of the seabed End Nov 2018 Early Jul 2019
Installation of a new crane Jul 2019 Jan 2020
Installation of shore engineering services Sep 2019 Jan 2020
Installation of wharf furniture Nov 2019 Jan 2020
Phase 2
Set-up of site Jan 2020 Feb 2020
Demolition of the existing wharf Feb 2020 May 2020
Construction of the new wharf May 2020 May 2021
Installation of shore engineering services Apr 2021 Jun 2021
Installation of wharf furniture Apr 2021 Jun 2021
Handover/takeover - Feb 2022